Prado Valley One HOA Road Project

November 2025

The HOA will be performing road improvement projects within the HOA boundaries. Improvements are limited to available funds. Road improvements are prioritized by safety first, then vehicle traffic on each road ~

ROAD SAFETY PROJECTS

November 15, 2025 – Rocky Bluff Road Stabilization & Erosion Control Project

HOA volunteers installed a 32′ Gabion wall in the arroyo below Rocky Bluff Rd. Todays team of volunteers were: Mike Stotts – appropriating the Gabion material, tractor work, rock hauling, and Gabion assembly; Jack Bassett -backhoe trenching and rock hauling; David Shavor, Andy McWhirter, Mark Ritchie, Leonard and Cindy Valdez – Gabion assembly, rock brigade and shovel work. It was a long day of hard hands on work. Additional time is required to complete the filling of the Gabion with rocks. If you are a community member and would like to volunteer to assist with filling the Gabion, please reach out to an HOA road committee member.

September 2025

    1.  Install speed bumps with caution signs.  We will start on Fort Delfina Rd.  within HOA boundaries and add speed bumps with signage to other roads pending funding availability.  Driving at excessive speeds is unsafe and will damage the roads.  – Completed
    2.  Install “One Lane Roads and Bridges” signage on Bean Creek Rd.  –Completed
    3.  Add additional roadside reflectors on Rocky Bluff –

      Completed

Road Improvement Projects  Ongoing

Note: Grading projects are weather dependent. Grading during dry periods overall will degrade the road. Grading projects and road bar ditch improvements will be performed after rain events.

    1. Grade Bean Creek up to Buffalo Trail.
    2. Cover exposed culvert on Buffalo Trail.  Completed
    3. Improve road drainage, erosion, and bar ditches.  Drainage ditch will reduce the possibility of road washouts that are expensive to repair.
    4. Grade other roads as budgets allow.